Padawan
Municipal council Chairman, Lo Khere Chiang said the temporary
diversion of roads could be completed in only two days time along the
stretch of Puncak Borneo between Kpg Karu, Kpg Bayur, Kpg Simuti and Kpg
Sibakar and Kpg Begu once the two huts which was in the way of the new
road were to be relocated.
The road along the stretch caved in causing road erosion and blocking
the shorter route to these kampongs. At the moment, the villagers have
to use another route which is half an hour further away.
Lo said the opening of the road to the public will undoubtedly bring a
huge relief for local commuters as well as tour operators.
Pointing out that he is always concerned when road erosions occurred
in areas affecting villagers, Lo said it affected their daily lives as
some of them would be cut off completely due to the only road they have
there.
He said in such occasion, the council would work with the JKR and
their engineers to start investigation to ascertain the causes of
failure and possible solutions to address the failed embankment.
“Embankment failure needs careful attention as the way water flows
under the ground to cause this kind of failure is sometimes very
unpredictable. As the project will take some time to complete with
detail design considerations, a temporary road diversion was considered
the best alternative to overcome immediate needs to relieve the many
commuters daily,” he said.
However, Lo pointed out that with an alternative road, the issue of
trespassing existing property has to be dealt with first. Thus, the need
to demolish two huts to achieve the proposed access and compensation
arises. He said he was thankful that though the efforts of
Infrastructure development, Dato’ Sri Michael Manyin, the compensation
was resolved.
On June 10, Lo said there was the mobilization of equipment to the
site and earthworks started the next day where they cut and filled on
two hills to allow a wider access for the proposed road diversion. An
area was cut and leveled for the relocation of landowners’ huts as part
of the negotiated agreement.
He said a five feet wide culvert was laid on June 12 and earthworks
continued, with the filling of a slope on the western side of the
failed embankment, to widen the access of the proposed diversion.
The whole major earthwork was done three days later and a temporary
gravel access has been constructed for motorcycles to use as an
immediate relief to them.
“JKR is now waiting for compensation to be disbursed to owners of the
affected huts and the relocation of these huts to proceed further. Once
relocation exercise is complete, stones as road base will be laid and
compacted,” he added.
Lo who is an engineer himself said the recent road collapses in
Penrissen and Padawan proved that the relevant authorities need to
relook at the construction of road designs to prevent such incidents.
He suggested construction of more small bridges across road sections
so that they could have intersecting waterways underneath which give
more solid foundation.
Meanwhile, on the Kpg Sadir bridge which collapsed after a lorry
drove through it early March this year, Lo said villagers can now use
the RM300,000 bailey bridge which was constructed and competed two weeks
ago.
The collapse of the bridge had affected 2,000 villagers and road users in Jalan Padawan Ulu.
Supp News: June 20, 2015